Showing posts with label factories. Show all posts
Showing posts with label factories. Show all posts

Tuesday, August 11, 2026

Siemens PCS7 (TIA) PowerControl Station Gateway connects PLCs with IEC 61850 IEDs

In a post earlier today I wrote: "It does not make sense to decouple power systems from big(ger) applications." ... this reminded me to discuss another use case ... factory automation to substation ...

Siemens offers PLCs with the PCS7 family. They have developed gateways that bring the substation closer to the power user ... 

PCS 7 PowerControl Station Gateway connection of a SIPROTEC 5 protection device (speaking IEC 61850!)

The brochure states at the beginning: "In addition to the demanding process automation requirements in many industrial plants, it is also necessary to integrate the medium-voltage power supply switchgear into a complete automation system.

Components of such plants are electrical consumers with high energy requirements (factories, chemocal plants, ...). Individual consumers are monitored and controlled via protection devices, also known as IEDs (intelligent electronic devices)."

So, my statement on the post earlier today has been confirmed! 

The same is available for the integration of a substation into a Siemens TIA (Totally Integrated Automation) ... TIA Station Gateway: excerpt of that page:

"With the new IEC 61850 server functionality, you can extend your station gateway integration allowing you to reliably publish process data directly to IEC 61850 clients via GOOSE Publisher or MMS polling and reporting with a high degree of performance. Whether protection systems, instrumentation and control or automation environments: The publisher ensures that events are quickly transferred and facilitates fixed data models and the highest degree of interoperability."

WOW.

Monday, February 23, 2026

What is the Scope of the IEC 61850 Series?

The seven IEC 61850 CDVs published the other day (7-4, 7-4n and 7-4nn) use all the same Scope which starts:
Excerpt from:
Communication networks and systems for power utility automation – Part 7-4: Basic communication structure – Compatible logical node classes and data object classes – Core
-------------
1.1 General
This part of IEC 61850 specifies the information model of devices and functions generally related to common use regarding applications in systems for power utility automation. In particular, it specifies the compatible logical node names and data object names for communication between intelligent electronic devices (IED). This includes the relationship between logical nodes and data objects.
...
This standard and its direct counterparts (7-4, 7-4n and 7-4nn) are applicable to describe device
models and functions for:
substation and feeder equipment,
substation-to-substation information exchange,
substation-to-control centre information exchange,
power plant-to-control centre information exchange,
• information exchange for distributed generation,
• information exchange for distributed energy resources,
• information exchange for metering,
• information exchanged for hydro power plants, or
• information exchange for wind generation plants.
--------------
The main title of all parts of the series IEC 61850 is: 
Communication networks and systems for power utility automation 
This title is some how an indication of the scope.
IEC 61850 can be used everywhere as follows:
Communication networks and systems for power utility automation
The narrow scope to power utilities is sometimes used by people that do not like the IEC 61850 series ... or do not want to let people outside the power utilities to apply it ... 
But the crucial content of the many different parts is applicable in most automation domains ... where ever electric power is found - buildings, factories, ... 
A lot of Logical Nodes, e.g., STMP (Supervision of Temperatures) are useful for transformers, bearings, tanks, ... 
Lessons learned:
  1. The various parts of IEC 61850 are applicable far beyond of the written scope - if you like it or not.
  2. Often the discussion related to the scope is aimed to tell you, that IEC 61850 is not applicable outside power utilities (or substations) - trust me: it is applicable far beyond.
By the way, the discussion of scopes could be ridiculous: IEC 60870-5-104  defines:
"This part of IEC 60870 applies to telecontrol equipment and systems with coded bit serial data transmission for monitoring and controlling geographically widespread processes. It defines a telecontrol companion standard that enables interoperability among compatible telecontrol equipment"
IEC 60870-5-104 does not have substation automation (usually not a widespread area) in its scope - BUT, you know 104 is used as the communication inside many substations! Ok ... why not. But then also IEC 61850 can be used for telecontrol ... see IEC 61850-80-1, ...
In the wind power industry it was discussed some 20 years ago: IEC 61850 is not applicable for wind turbines, because wind turbines are not substations ... hahaha
Enjoy IEC 61850!