Friday, January 27, 2012

IEC 61850 in the U.S. – A Personal View of IEC 61850

Scott Olson (POWER Engineers) investigated recently to figure out the situation of the application of IEC 61850 in the U.S.: He found IEC 61850 on the radar screen!

In his report (A personal view of IEC 61850) he wrote early January 2012 that IEC 61850 is “More Than a Protocol”. Yes – it is much more than a protocol. It is not something like “DNP4” or “IEC 60870-5-105”. The standard series IEC 61850 provides a bunch of definitions applicable in many different subsets – there will never be an implementation that implements the whole standard series! Never ever.

Some explanation on basic concepts of the standard series IEC 61850 follow (before we have a closer look into Scott Olson’s report):

IEC 61850 provides models of real world information (status, measurements, and control points, settings, …) for many different application domains. The following slide shows an example of a model: XCBR – circuit breaker of a real substation.

image

Another area is the system configuration language (SCL) that describes many aspects of devices and the whole system. Third, there is the communication shown in the top left corner. The communication defines services. These services are realized by protocols. The protocols are comprising TCP/IP based client-server communication and Ethernet based real-time communication (GOOSE and sampled measured values – sensor-data).

Protocols are needed – the crucial issues are models and configuration language.

Some of the services that communicate the state-changes of the circuit breaker are as follows:

image

Is it worth to compare the protocols of various standards? Check the following table to figure out what the left side has to offer … and what the standards on the right have:

image

IEC 61850 is mainly focusing on crucial aspects of the many applications and on the system – system means: what to communicate, from where to where, how to communicate, when, … how to configure systems and devices, how to document requirements and systems, …

A remaining question is: What is most important to look at or to implement or to apply? It depends. From a device point of view it is absolute important to have the communication services and protocol – and application program interface (API) – implemented. This is required in TWO devices – the server, that provides the models, and the client that reads values or receives spontaneous reports:

image
From a application point of view it is crucial to look at the models!! ;-)

The models should be discussed independent of ANY protocol!!! Many people have understood that the models, services and protocols of IEC 61850 are all independent of each other – that is one of the crucial benefits! That is the reason why IEC 61400-25-4 (Wind Power application of IEC 61850) defines the mapping of process values (the signal lists) and simple services to DNP3 and IEC 60870-5-101/104. Because the models, services and configuration language are independent of the protocols.

And also note that the use of IEC 61850 is first of all intended for the substation automation and power generation … finally it may be used (in the long term) in the communication with control centers.

Back to the crucial lessons Mr Olson and others have learnt:

He writes: “We received a great email from one of our readers, who reminded us that there was a difference between a standard and a protocol—the latter being a component of the former—and that it was possible to implement IEC 61850 protocols without going all out to implement the standard.

"For example," our reader offered, "61850 GOOSE messaging may be used between IEDs to eliminate physical wiring and increase speed of interaction between IEDs while continuing to use DNP to communicate upwards to SCADA and higher-level systems where slower communications updates are acceptable.

It was such a great point to make: The migration to the IEC 61850 standard does not force the absolute replacement of protocols that are already in place. Solutions can be implemented that allow parts of 61850 to be added to the network while the legacy protocols continue to be used over the same network. For example, station bus protocol (IEC 61850-8-1) could be used to simplify the
interface between IEDs, human-machine interfaces (HMIs), etc. within the substation network while continuing to use DNP interface to SCADA. As process bus (IEC 61850-9-2) devices become readily available, the opportunity to eliminate copper wiring between current transformers (CTs) and IEDs could provide tremendous …”

The lesson that everybody should learn soon (or should have learnt): IEC 61850 could be implemented in many different subsets for even more simple to complex applications. I hope that at the end of 2012 the universe has understood that the standard series IEC 61850 is more than just a protocol – it goes far beyond DNP3, IEC 60870-5-101/104, even beyond OPC and OPC UA! It’s a system-supporting solution.

By the way, this blog is visited by many experts from North America. It is likely that Mr Olson’s lesson will be read by many U.S. people.

Click HERE for the full “personal view”.

In a open job description for an Automation Engineer in Rochester (New York) I just read today (2012-01-28) the following:

Requirements:
MUST HAVE
…
Knowledge of digital projection
Knowledge of IEC 61850
Knowledge of communication protocols- DNP

Know SCADA systems manufacturers and equipment
…

IEC 61850 and protocols are two things!

Wednesday, January 11, 2012

Description of IEC 61850 Application Examples

A couple of application examples using IEC 61850 for substation protection and automation can be found in a 48 page brochure from Siemens (English and German).

The following topics are covered:

  • Switchgear Interlocking with IEC 61850-GOOSE
  • Reverse Interlocking Using the GOOSE of IEC 61850
  • Beneficial Engineering of IEC 61850 Substation Automation Systems
  • Innovative Solutions for Substation Control with IEC 61850
  • Seamless Migration
  • Ethernet Topologies with IEC 61850
  • IEC Interoperability,Conformance and Engineering Experiences
  • IEC Browser – A Powerful Test Tool for IEC 61850

The description is to a large extent vendor-neutral.

Click HERE for the English version [pdf, 1.4 MB]
Click HERE for the German version [pdf, 1.4 MB]

Sunday, July 10, 2011

Is IEC 61850 Plug&Play or like DNP4.0 or IEC 60870-5-105?

There are many different expectations I heard from protection and control experts all over. Some people guess that IEC 61850 provides Plug&Play capabilities – meaning: Utilities just purchase IEC 61850 IEDs and (all in a sudden) their protection and control systems are up and running! There is a group of other people that expects that IEC 61850 is just another protocol – a bit more than today’s solutions … something like “DNP4.0” or “IEC 60870-5-105” [of course DNP4.0 and 105 are not real!].

IEC 61850 is much more than DNP3.0 and IEC 60870-5-104, and it does NOT provide Plug&Play. Building substation protection and control systems requires to understand the applications (the many protection and protection related requirements) and to find a way how to apply IEC 61850 compliant IEDs and tools to solve their many needs.

IEC 61850 is a suite of tools that can be used to solve application needs. How to use the tools and when, is NOT defined in the standard! Utilities have to find their (step by step) way to get started with IEC 61850 based solutions. It is important to get started – don’t wait until IEC 61850 solves all your needs and problems. This will never happen!

Some US experts have discussed in 2005 or early 2006 what IEC 61850 provides and what needs to be done to apply the standard and standard based solutions. They show that IEC 61850 has an impact on many aspects in system design and deployment.

IEC 61850
A Practical Application Primer for Protection Engineers
Bogdan Kasztenny, James Whatley, Eric A. Udren, John Burger, Dale Finney, Mark Adamiak

Click HERE for the 43 page paper – worth to read.

My hope is that readers of the paper (hopefully readers from the utilities – or students finishing their education soon) understand that IEC 61850 requires utility people that are well educated in IEC 61850 – in order to understand what the big vendors have commissioned and how to use the various features of the new design.

Today I received an email from one the international biggest transmission utilities asking for help in better understanding what is needed and what has been commissioned:

“Karlheinz, …. As you probably know, there are more and more digital substations in XXX, provided by XXX and XXX for the time being. Even if our contracts does not specify explicitly the use of 61850, they are based on this standard. Today, these substations can be viewed as black boxes, without really taking into consideration the advantages of new digital technologies. …”

One of the crucial needs is: MORE EDUCATION FOR UTILITY EXPERTS!! I have met many utility people that were responsible for the substations based on IEC 61850 – but DID NOT any clue how to use IEC 61850 build in functions.

IEC 61850 has a crucial impact on the WHOLE system and the engineers that build systems.

Finally, SCADA applications (to get status changes, limit violations, measurements, statistical information, historical information, …) can apply IEC 61850 right away with commercially available Off-The-Shelf (COTS) solutions like the well appreciated Windows DLL for IEC 61850 (applicable for servers, clients, publishers, and subscribers).

Click HERE for a Windows DLL evaluation kit with an C# application example including source code of the client and server applications (that use the DLL).

Tuesday, December 23, 2008

Various applications of IEC 61850 explained

An explanation of several applications of IEC 61850 can be found in a nice 48 page brochure published by Siemens (in English and Deutsch):
  • Switchgear Interlocking with IEC 61850-GOOSE
  • Reverse Interlocking Using the GOOSE of IEC 61850
  • Beneficial Engineering of IEC 61850 Substation Automation Systems
  • Innovative Solutions for Substation Control with IEC 61850
  • Seamless Migration
  • Ethernet Topologies with IEC 61850
  • IEC Interoperability, Conformance and Engineering Experiences
  • IEC Browser - A Powerful Test Tool for IEC 61850