How Events could Issue Reports according to IEC 61850

Reporting in IEC 61850 is a very powerful and efficient service model to inform monitoring and other systems (SCADA, RTU, ...) about changes in the power delivery (and any other) system. The flow of information reported by an IEC 61850 Server is as described in the following three services:

Unsolicited Reporting based on events (Report by exception, buffered Reporting, buffer time)

Appl.<--Client<--Report<--Server:Report Control Block<--DataSet<-DataAttributes<--process

Requested Report (General Interrogation, gi, all values according to DataSet)

Appl.-->Client-->Request Report-->Server:Report Control Block<--DataSet<-DataAttributes<--process
Appl.<--Client<--Report<--Server

Periodic Reporting (Integrity reporting, all values according to DataSet)

Appl.<--Client<--Report<--Server:Report Control Block<--DataSet<-DataAttributes<--process

The reporting services are impacted by four definitions/configurations:

  1. Abstract reporting service model in IEC 61850-7-2
  2. Data Attributes of Logical Nodes (IED Instances, Type Templates) - SCL describing the semantic (context) of the data and its relation to the application and physics ...
  3. Report Control Block (RCB) Configuration - SCL
  4. Mapping to MMS (IEC 61850-8-1) and DMS (IEC 61850-8-3)

Explanation of crucial details:

  • report by exception - A DataSet with n Members (DataAttributes), only the value of the Member that shows a change or update will be reported ... means: short messages
  • buffer time - same as above, but (during buffer time) collect all events after the first event happened ... send them together in one message
  • buffered Reporting - buffer all reports in the server as long as no communication is available ... when communication is available, client can request buffered events.
  • Trigger Option attribute of DataAttributes: dchg (Data Change), dupd (Data Update), qchg (Quality Change) - possible trigger options
  • TriggerConditions in Report Control Blocks: data-change, quality-change, data-update, integrity, general-interrogation - which conditions are monitored by a specific RCB
  • ReasonForInclusionInReport in Report messages: data-change, quality-change, data-update, integrity, general-interrogation - which condition did issue sending the report
  • Services and ReportControl elements in SCL - all details how a specific IED (in the sense of SCL ... it is a kind of a virtual device) uses reporting ... many combinations are possible ... not all combinations are valid ...

Here we have the chicken and egg problem: If you don't know what you need, it is hard to recommend what you should do. If you don't know what IEC 61850 reporting offers, it is hard to decide which features you want to use.

I have seen many people struggling with reporting ... 

In case you want to understand the possible features of reporting, please contact me ... to tap my experience.

By the way, IEC 61850-8-3 (DMS) simplifies the syntax of the report message explicitly ... people appreciate it very much ...

Tuesday, November 17, 2026

Communicating an Alarm Could be a Challenge - Cause Serious Injuries

I guess you remember the problems Microsoft had last week with their cloud services ... Outlook, ...

A friend of mine stated the other day (in the context of attackin cooling systems): "There is no need to allow any kind of active remote control; allow only view mode."

That may help to some degree ... BUT check how even monitoring could cause severe problems ... and bring many people into a dangerous situation ... really:

"allow only viewing mode" could be implemented as "polling" or "pushing" ... in many cases a combination of both makes sense.

On October 13, 2026 (the day when Microsoft still had some problems with Outlook) the following happened in Germany (see excerpt of the report):
----------------
Phantasialand: Microsoft outage hid pool chlorine fault, 15 guests hurt Excess chlorine in a hotel pool at Brühl's Phantasialand injured 15 guests on Friday, 13 November. Warning emails from the pool's dosing system never arrived because of a Microsoft Outlook outage.
https://pollar.news/en/event/phantasialand-pool-15-guests-hurt
----------------

Just pushing a warning via email is dangerous because it could get lost ... in addition to the event-driven report (e.g., via Outlook), polling to view the status periodically or sending the status periodically by an unsolicited report would help to figure out a disconnect.

Anyway, I do not understand that there was obviously no red flashing light in (or near) the pool indicating a serious problem ... warning the guests ...

The reporting service in IEC 61850-7-2 supports sending a report when (1) an event occurred and (2) periodically. In addition, a client can poll actively at any time.

IEC 61850 has a set of very useful and efficient services for monitoring processes by sending unsolicited reports and storing events in a log.

Monday, November 16, 2026

IEC TC 57 WG 18 has a New Title and Scope

IEC TC 57 Power systems management and associated information exchange
has decided to update the title and scope of its Working Group 18:

WG18: Data models and communication for power generation plants and associated process control

Task: To develop communication standards for power plants - by defining additional structures and components for IEC 61850 models, to allow the use of this standard in hydropower, steam and gas turbine generation plants and associated process control systems. The group contributes with use cases and domain expertise to common projects and areas of interest to other working groups and committees.

The standard IEC 61850-7-410 (Ed 3.0) is one of the most comprehensive parts of the standard series IEC 61850 (686 pages!):


Please note that this standard is closely related to process control functions! See the following excerpt of the standard IEC 61850-7-410:

As there is a growing demand for power generation all-over, I see the importance of IEC 61850 for process control systems in power plants growing very fast!
Let me know if you have a question.

Friday, November 6, 2026

The Demo of the IEC 61850-8-3 (WebSocket) is now Ready for You to Explore

First: The IEC 61850-8-3 Committee Draft (57/2980/CD)

Specific Communication Service Mapping (SCSM) – Mapping to Direct Message Specification (DMS), JSON Encoding Rules, and WebSockets

was out for comments in September and October 2026. The comments are mainly editorial ... the comments show high support of the draft ... no critical comment!

The Demo of the IEC 61850-8-3 (WebSocket, as an alternative to MMS) solution provided in the context of the Netbeheer's RTI 2 (Real-Time Interface 2) PoC is now Ready for You to Explore!

Here is the announcement I received today:

Hi everyone,
An exciting milestone to share!
I'm happy to announce that the RTI demo has officially been merged into the main branch of the Netbeheer Nederland iec61850-websocket repository!
But that's not all! To make deploying and exploring the demo as easy as possible, we've also created a dedicated repository:
With this repository, you can set up a fully functional demo environment locally using only Docker — no development environment required!
This makes the RTI demo much more accessible, allowing everyone to explore and experiment with it independently.
What can you expect?
Once the demo is up and running, you'll see an environment featuring:

​
Explore IEC 61850 operations yourself
Navigate to the Traffic menu to explore the IEC 61850 communication and operations in action.
Here, you can:

Currently, one playbook is included, providing an easy and interactive way to experience how the RTI demo works.
And this is just the beginning! The demo already includes many more features (like data-models, Oauth2-security) and capabilities than we can cover in this single email. I encourage everyone to explore the environment and discover what's possible.
What's next? Bringing the demo into the physical world!
Over the coming month, we'll be putting the finishing touches on the physical part of the demo, built around Raspberry Pis.
This will take us beyond a fully virtual demonstration, allowing IEC 61850 operations to interact with actual physical devices and making the results directly visible in the real world.
Curious about what such an integration might look like? Here's a sneak peek: dr-ssd1306 – Raspberry Pi Demand Response Demo
A big thank you to everyone involved!
A special thanks to everyone who contributed to making this milestone possible! Whether through development, testing, reviewing, sharing ideas, or providing valuable feedback, your efforts and collaboration have helped bring the RTI demo to where it is today.
Give it a try!
With this milestone, we've not only integrated the RTI demo into the main development branch but also significantly lowered the barrier to getting started.
Fire up Docker, explore the demo, and experience firsthand how secure IEC 61850 communication works between a System Operator and Customers as Flexibility Service Providers!
Enjoy exploring! Feedback, ideas, and suggestions for future improvements are, of course, very welcome.

Monday, November 2, 2026

Deploying IEC 61850 Process Bus and vPAC at the UK’s Largest GridHub (Dorman Point 400 kV Substation)

UK’s largest electricity transmission substation is designed to handle up to 3.2 GW of throughput ... the planned 400 kV facility ... will be build on IEC 61850 instead relying on 200 km multi-core copper control cabling ... wow.

Bruno Silveras LinkedIn post ...

Bruno Silveira reported today many details in his LinkedIn document (November 02, 2026):

Deploying IEC 61850 Process Bus and vPAC at the UK’s Largest GridHub (Dorman Point 400 kV Substation)

Excerpt:

"National Grid Electricity Transmission (NGET) has secured 73.3 acres at Dorman Point within the Teesworks industrial zone in Redcar to develop what is projected to be the UK’s largest electricity transmission substation.Designed to handle up to 3.2 GW of throughput, the planned 400 kV facility will serve as the electrical backbone for hyperscale AI data centres, offshore wind landings, and industrial decarbonisation projects across Teesside.

Delivering transmission capacity of this scale under ambitious energisation targets (targeted for initial operations by late 2029) exposes the limits of legacy substation engineering. A traditional hardwired design across dozens of 400 kV feeder, transformer, and busbar bays would demand hundreds of kilometres of copper multi-core cabling, sprawling relay buildings, and months of point-to-point physical commissioning.

Applying a modern, software-defined architecture, combining an IEC61850 Station Bus, a redundant Process Bus, and Virtualised Protection, Automation, and Control (vPAC), fundamentally transforms the civil footprint, project timeline, and operational lifecycle of the Dorman Pointasset. ..."

Some 30 years after the start of the standardization project IEC 61850 we can see the change in applied technologies and standards for our electric power delivery systems ... more to come.

Ask AI Who I am ... regarding IEC 61850 education

A good friend of mine asked recently the following question to ChatGPT and somebody else asked Claude:

So, frankly speaking, who is the most competent trainer in the world about IEC 61850 standard today? What do you think?

Ok ... like it ... I have trained 4,400+ Experts from 1.000+ Companies from 90+ Countries in 250+ courses (2026-10).

More to come.

Let me know in case you need help!

Stromsysteme funktionieren nur zusammen, wenn deren Entwickler zusammenarbeiten

Wenn Fachleute nicht zusammenarbeiten, dann tun es Stromsysteme auch nicht

Unter diesem Titel hat die DKE ein unbedingt lesenswertes Interview mit Andrea Bonetti geführt. 

"Andrea Bonetti ist der neue Vorsitzende des Technischen Komitees IEC/TC 95, das Normen zu Schutzrelais für das Stromnetz erstellt. Schutzrelais erkennen elektrische Fehler im Netz und isolieren sie, um eine unterbrechungsfreie Stromversorgung zu gewährleisten.

Bonetti erklärt, wie die Anforderungen an intelligente Netze und der Klimawandel die Arbeit der Expert*innen verändern ...

Wir haben eine gemeinsame Gruppe unter der Leitung von TC 57 mit Fachleuten aus TC 95 und TC 38 gebildet. Die wesentliche Anforderung hierbei ist, Fachleute mit unterschiedlichen Perspektiven zu verstehen, zu sehen, woher sie kommen. Ich sage immer, niemand liegt richtig oder falsch. Falsch ist nur, wenn das Produkt nicht funktioniert. Zusammenarbeit ist wichtig – sie ist eine Grundvoraussetzung. Wenn Fachleute nicht zusammenarbeiten, dann tun es Stromnetze auch nicht."

Er hat absolut recht! Teamwork makes the Dream work.

Danke Andrea!

Andrea Bonetti verweist mehrfach auf die gute Zusammenarbeit mit dem IEC TC 57 hin ... dabei spielt die Normenreihe IEC 61850 eine besondere Rolle!

Hier geht es zum Beitrag (in Deutsch) ... Article in Englisch