Deploying IEC 61850 Process Bus and vPAC at the UK’s Largest GridHub (Dorman Point 400 kV Substation)

UK’s largest electricity transmission substation is designed to handle up to 3.2 GW of throughput ... the planned 400 kV facility ... will be build on IEC 61850 instead relying on 200 km multi-core copper control cabling ... wow.

Bruno Silveras LinkedIn post ...

Bruno Silveira reported today many details in his LinkedIn document (November 02, 2026):

Deploying IEC 61850 Process Bus and vPAC at the UK’s Largest GridHub (Dorman Point 400 kV Substation)

Excerpt:

"National Grid Electricity Transmission (NGET) has secured 73.3 acres at Dorman Point within the Teesworks industrial zone in Redcar to develop what is projected to be the UK’s largest electricity transmission substation.Designed to handle up to 3.2 GW of throughput, the planned 400 kV facility will serve as the electrical backbone for hyperscale AI data centres, offshore wind landings, and industrial decarbonisation projects across Teesside.

Delivering transmission capacity of this scale under ambitious energisation targets (targeted for initial operations by late 2029) exposes the limits of legacy substation engineering. A traditional hardwired design across dozens of 400 kV feeder, transformer, and busbar bays would demand hundreds of kilometres of copper multi-core cabling, sprawling relay buildings, and months of point-to-point physical commissioning.

Applying a modern, software-defined architecture, combining an IEC61850 Station Bus, a redundant Process Bus, and Virtualised Protection, Automation, and Control (vPAC), fundamentally transforms the civil footprint, project timeline, and operational lifecycle of the Dorman Pointasset. ..."

Some 30 years after the start of the standardization project IEC 61850 we can see the change in applied technologies and standards for our electric power delivery systems ... more to come.

Ask AI Who I am ... regarding IEC 61850 education

A good friend of mine asked recently the following question to ChatGPT and somebody else asked Claude:

So, frankly speaking, who is the most competent trainer in the world about IEC 61850 standard today? What do you think?

Ok ... like it ... I have trained 4,400+ Experts from 1.000+ Companies from 90+ Countries in 250+ courses (2026-10).

More to come.

Let me know in case you need help!

Stromsysteme funktionieren nur zusammen, wenn deren Entwickler zusammenarbeiten

Wenn Fachleute nicht zusammenarbeiten, dann tun es Stromsysteme auch nicht

Unter diesem Titel hat die DKE ein unbedingt lesenswertes Interview mit Andrea Bonetti geführt. 

"Andrea Bonetti ist der neue Vorsitzende des Technischen Komitees IEC/TC 95, das Normen zu Schutzrelais für das Stromnetz erstellt. Schutzrelais erkennen elektrische Fehler im Netz und isolieren sie, um eine unterbrechungsfreie Stromversorgung zu gewährleisten.

Bonetti erklärt, wie die Anforderungen an intelligente Netze und der Klimawandel die Arbeit der Expert*innen verändern ...

Wir haben eine gemeinsame Gruppe unter der Leitung von TC 57 mit Fachleuten aus TC 95 und TC 38 gebildet. Die wesentliche Anforderung hierbei ist, Fachleute mit unterschiedlichen Perspektiven zu verstehen, zu sehen, woher sie kommen. Ich sage immer, niemand liegt richtig oder falsch. Falsch ist nur, wenn das Produkt nicht funktioniert. Zusammenarbeit ist wichtig – sie ist eine Grundvoraussetzung. Wenn Fachleute nicht zusammenarbeiten, dann tun es Stromnetze auch nicht."

Er hat absolut recht! Teamwork makes the Dream work.

Danke Andrea!

Andrea Bonetti verweist mehrfach auf die gute Zusammenarbeit mit dem IEC TC 57 hin ... dabei spielt die Normenreihe IEC 61850 eine besondere Rolle!

Hier geht es zum Beitrag (in Deutsch) ... Article in Englisch